Case Study: Wellpoint Dewatering

 

 

One of the largest agricultural irrigation districts in the U.S. needed to replace one mile of failed pipeline in less than six days to avoid millions of dollars of crop damage.

Because of the high water table in the earthquake-prone area, the district wanted high-quality material and services to make the pipeline stronger and last longer than it had previously.

Rain for Rent had six days to install the dewatering system. Two jetting crews worked to instal 85-90 wellpoints per day while a third crew installed the one-mile long discharge pipe and pumps.

Rain for Rent used two DV150c PowerPrime pumps to discharge the water removed from the wellpoint dewatering system.